Voldrogue School Construction Update – January 26, 2012
The construction on the new school in Voldrogue was begun on December 11, 2011. The excavation for the foundations of the Preschool and Administration buildings was completed prior to Christmas.
After a break for the Holiday season, work resumed during the week of January 9. As of January 21, the foundations of the Preschool building were complete and work was proceeding on the columns, deck beam and other components of the main floor of the building.
The Primary School Building was laid out by Architect Jason Krumm, Engineer Patrick Duval and General Foreman Mondy Pamphile on January 20 2012. Work will begin on that building in the next week or so. We will use a front loader with a backhoe to do the necessary excavations, including the cisterns that will be located under that building.
Click each thumbnail below to view the image in full size.
- Preschool Building Construction Site – January 20, 2012
- Preschool building construction site with Clinic Building – January 20, 2012
- Ironworkers fabricating reinforced concrete columns
- Due to soil conditions, it was necessary to dig the foundations of the Administration Building deeper than anticipated. Stable soil was found at about 1.2 meters. Foundation work is now moving ahead on the Administration building.
- Architect Jason Krumm, Engineer Patrick Duval and General Foreman Mondy Pamphile using triangulation to ensure the location of the new Primary School building is correct.
- Truck unloading sand for the construction project.






