Construction on the Sassier School continues to move along fairly well. Although the iron and carpentry work for the pouring of the first half of the roof of the large building was complete before the end of the year, the actual pouring could not be accomplished...
Jan 27, 2012
The construction on the new school in Voldrogue was begun on December 11, 2011. The excavation for the foundations of the Preschool and Administration buildings was completed prior to Christmas. After a break for the Holiday season, work resumed during the week of...
Jan 18, 2012
A team of medical professionals from Holland Hospital in Holland, Michigan is on the ground this week in Sassier, providing primary medical care in both Sassier and Voldrogue (about 45 minutes from Sassier). Please view our pictures below, and learn more about this...
Jan 3, 2012
On December 11, we broke ground for a new preschool and primary school building in Voldrogue, about 45 minutes’ walk from Sassier, although still in the Sassier Parish. For a number of years, children from Kindergarten to 3rd grade have been attending school in...
Jan 3, 2012
Work on the construction of the new preschool and primary school is now moving ahead very well. The 2nd floor roof on the smaller building was finished in mid-November. Work is now focusing on 2nd floor of the larger building, which should be complete in early...